JobBOSS | Ideas

 

Merged idea

This idea has been merged into another idea. To comment or vote on this idea, please visit JBCORE-I-7 Show/commit the actual material revision used for a particular job.

Material should have a revision no. Merged

It is helpful when purchasing complete part from an outside vendor.

If the material no is specified so purchaser know what drawing revision to order.

Incoming inspector can pull the correct drawing revision.

Traveller only shows material no and not the revision no and assumes latest revision.

At times customer order parts from both revisions to meet their requirements.

  • Rojar Patel
  • May 12 2017
  • Future Consideration
  • Guest commented
    May 18, 2017 19:49

    Agreed! We also need revision fields when buying materials.